Roadwork begins at Winter Street, Park Drive intersection in Rockland
Mon, 11/03/2025 - 4:28pm
ROCKLAND — Beginning Tuesday, November 4, as part of improvements to Rockland's stormwater infrastructure, crews will begin work at the intersection of Winter Street and Park Drive. Traffic will be routed around this construction via Commercial Street, Weeks Street, and Tillson Avenue. The work should take between 2 and 3 days.
City of Rockland
Schedule: Oak & Orient Street Improvement Project
Week of September 29- October 3:
- Main Street sewer; core into existing SMH, install SMH#2 & SMH#3
Week of October 6- November 14:
- Install storm drainage pipe & structures; Park Drive, Winter Street, Key Bank, through Main Street
Week of November 17- December 15:
- Install storm drainage pipe & structures; Oak & Orient Streets