Ragged Mountain Foundation pays half of Camden’s $743,134 Snow Bowl shortfall
The Ragged Mountain Recreation Area Foundation delivered a check to the Camden Select Board Tuesday evening, May 2, making good on its promise to fund 70 percent of costs associated with the Camden Snow Bowl redevelopment. However, the Foundation is waiting for a more detailed fiscal picture of project expenditures before reimbursing more money.
“After review and thoughtful consideration, the Foundation remains committed to the project and will pay the current shortfall of $743,000 out of existing funds earmarked for this project,” said Foundation President Bob Gordon, reading a letter to the town at a regularly scheduled Camden Select Board meeting.
“We will make an immediate payment of 50 percent and the remaining 50 percent as soon as the town provides a breakdown of the expenses in the major cost centers,” he said.
(See attached PDF or below for Gordon’s entire letter)
Gordon stood at the podium in the Washington Street Conference Room, presenting the Foundation’s position on an issue that has occupied the town since one citizen began questioning the town’s fiscal history with the redevelopment. (Read: Camden and the Snow Bowl redevelopment: One citizen's inquiry into the cash flow)
Gordon spoke for approximately 10 minutes during the public comment portion of the meeting. Gordon said after the meeting that the project donors wanted to see a more thorough breakdown of expenses associated with the redevelopment.
The Foundation is a local nonprofit that pledged to raise $4.5 million from private fundraising for the $6.5 million Ragged Mountain redevelopment project. Camden voters agreed to kick in $2 million to the project by issuing a bond. The project, which was set into motion in 2014, included wider trails, the purchase and installation of a used three-person chairlift, better snowmaking, and other mountain improvements. The $6.5 million was to also include a new lodge.
By 2016, however, the project costs had risen to $6.8 million, without a new lodge. The Foundation agreed in 2016 to continue to help raise additional funds for the new lodge, and estimating a total project cost of $8.5 million.
Gordon said May 2 that the Foundation wanted to see the new lodge constructed and would continue to raise funds for that final project piece.
“There is money still set aside for the new lodge,” said Gordon.
He said, reading from the letter, “The Ragged Mountain Recreation Area Foundation reaffirms its commitment to work with the Town of Camden and the greater Midcoast community in completing the project and thanks everyone who has supported this effort.”
After he finished, Gordon sat down and Foundation Treasurer Judy Sherman approached the front of the room and handed Board Chairman John French a check for half of $734,134.
That check represented half of what the town said it had failed to bill the Foundation for project expenditures.
Later in the meeting, as the Select Board discussed the town’s 2016 fiscal audit, independent auditor Chris Backman, of the Buxton-based R. H. Smith and Co., said the check would help the town’s rebuild its net equity, which had shrunk over the past two years, as the town’s fund balance had been reduced to levels below what is commonly acceptable for municipalities.
That depletion of the town’s unassigned fund balance is, in large part, the result of over-spending on the redevelopment from the town’s own coffers.
According to April 18 municipal meeting minutes: “The Selectmen and Interim Town Manager acknowledge that the over-expenditure figure of $743,134 has come out of the town’s General Fund and needs to be replaced.”
Auditors cited poor bookkeeping, unauthorized budget revisions and project change orders.
After the audit was finished, the Foundation and Camden’s Interim Town Manager Roberta Smith began to meet about the $743,134 that the town had absorbed.
“We have had numerous lengthy conversations and meetings with the auditor and town officials since the audit was commissioned and budget issues were brought to our attention,” said Gordon.
“Our goal, as donors and supporters, was to get a clear understanding of the financials and the status of the project. First, and most importantly, we were assured by the auditor that all monies donated and allocated were spent on the project-design and construction and ski area improvements on the mountain.”
Snow Bowl Manager Beth Ward said after the meeting that she would soon complete a spreadsheet of redevelopment expenditures going back to 2008. It would then be submitted to the Foundation, and available for public review.
Gordon said that: “the project should have been managed better by the Town of Camden and issues communicated in a timely manner. It is a complex project and many factors have contributed to the current situation.”
But, he said, the town would get the rest of the money following the more comprehensive breakdown of expenses.
“The money is coming as soon as you can get that,” he said.
LETTER TO THE COMMUNITY
Ragged Mountain Recreation Area Foundation (RMRAF): Response to the Town Redevelopment Project Audit
The Ragged Mountain Recreation Area Foundation, like many in the community, was anxious to review the audit of the Redevelopment Project and to gain an understanding into the status of the town-owned and managed project. We were as surprised as everyone else to learn of the significant recent cost overruns and current situation. After repeated requests to the former Town Manager over the past 18 months by the Ragged Mountain Recreation Area Foundation for financial updates and invoices, it took the efforts of a private citizen and Snow Bowl supporter to bring the project issues to everyone’s attention.
None of us wants to be where we are at this stage in the project, but unfortunately, we are. The Foundation feels a deep sense of responsibility to donors of the project, as well as to the citizens of Camden who have invested in our wonderful community asset. We are also committed to the completion and success of the project.
We have had numerous lengthy conversations and meetings with the auditor and Town officials since the audit was commissioned and budget issues were brought to our attention.
Our goal, as donors and supporters, was to get a clear understanding of the financials and the status of the project. First, and most importantly, we were assured by the auditor that all monies donated and allocated were spent on the project-design and construction and ski area improvements on the mountain. Phase 1 and 2 were completed and, by all accounts, are working extremely well. These phases included the newly refurbished triple and double lifts and a new magic carpet lift for beginners; trail work that included widening of existing trails to the top; and a new and expanded beginner area which was identified as a critical need for the mountain. Snowmaking capacity was more than doubled with all new systems; lighting was extended to the top of the mountain where the triple lift terminates; a new access road was built, which has facilitated mountain maintenance; the lower and upper parking areas were completed with the required storm water mitigation systems; and the septic and electrical systems were completed and ready for Phase 3 - the new lodge / community center.
That being said, the project should have been managed better by the Town of Camden and issues communicated in a timely manner. It is a complex project and many factors have contributed to the current situation. They fall into four big buckets based on our assessment.
- 1- Timeframe: The project has been underway for close to 8 years and some of the initial estimates were low. They were adjusted over the course of the project, but clearly the project costs increased over this lengthy period.
- 2- Project Management: There were issues of project and cost management and expense control on multiple levels, both on the mountain and in the Town office as identified by the audit. This was compounded by a lack of communication and transparency from the Town.
- 3- Project Changes: As the project evolved, change orders and expanded scope resulted in budget increases. In review, some changes were probably the right decisions based on the given issue or situation (such as new State lift regulations), and others could have been deferred or managed differently. Either way, changes should have been communicated early and often.
4- Other Issues: There were unforeseeable issues from the logging operation, weather, and other mountain challenges that arose during the project, such as erosion and the need for storm water mitigation that added additional costs.
Mistakes were made and lessons have been learned. We strongly concur with the auditor’s recommendation that, going forward, any new work must have bids, contracts in place, and a third- party professional project manager to proceed.
After review and thoughtful consideration, the Foundation remains committed to the project and will pay the current shortfall of $743,000 out of existing funds earmarked for this project. We will make an immediate payment of 50% and the remaining 50% as soon as the Town provides a breakdown of the expenses in the major cost centers.
Many factors have been critical in our reaching the above assessment and response. The Camden Snow Bowl/Ragged Mountain Recreation Area is vital to our community as a four season recreation area. The area provides over 65,000 recreation user days and that number is growing. Economically it contributes far more than many people realize, creating close to 70 fulltime and seasonal jobs. These jobs allow schooner captains, restaurant owners and workers, fisherman and many others to piece together rewarding and fulfilling year-round employment, which allows them to thrive and stay in the area.
An independent economic study conducted by Camoin and Associates in 2013 confirmed that the Ragged Mountain Recreation Area currently contributes over $4 million annually to the town/region from mid-coast residents and visitors from away with lodging, meals, other in town activities, equipment purchases, and direct dollars spent by employees, which will only increase once the project is completed. We have witnessed the impact of the recent loss of Saddleback Ski Area on the Rangeley, Maine Region and it has been nothing short of devastating. Once a ski area is gone, it is nearly impossible for them to claw their way back operationally. Prior to the Redevelopment Project, the Camden Snow Bowl was on the eventual path to closure with years of minimal to no investment, deferred maintenance, failing equipment, and systems that were not up to current standards and code.
In addition to the Foundation, other organizations whose staff and members are from the larger mid- coast area are investing significantly in the area; the Coastal Mountain Land Trust is investing over 4 million dollars to build the Round the Mountain trail and to protect additional land surrounding the ski area, and the Mid-coast Mountain Biking Association is working with the Town and multiple foundations to fund and expand cross-country and down-hill mountain biking (which will ultimately generate revenue through user fees during the spring , summer and fall, utilizing many assets owned by the Town and already in place).
Recent studies show that trail systems and recreational opportunities are one of the main attractions for people moving to or visiting an area, and increase local property values. The lodge/community center is the final piece of the equation and critical to these investments. It will provide much-needed space for increased usage, will be a gateway and attraction to the recreation area and will provide significant rental revenue from events to cover operating costs.
Lastly, and very importantly, the Camden Snow Bowl had a $94,000 profit/surplus this winter in a snow season, which by many accounts and statistically, was a below average year, with 54 inches of total snow. Clearly, the signs are there -a breakeven or profitable operation is more than achievable. As the Snow Bowl management team gets to know the new systems and optimizes efficiencies, the ability to operate in a sustainable manner is very realistic and achievable.
Finally, the Ragged Mountain Recreation Area Foundation reaffirms its commitment to work with the Town of Camden and the greater mid-coast community in completing the project and thanks everyone who has supported this effort.
Related stories:
Camden waits for $743,143 reimbursement for Ragged Mountain redevelopment
Camden Snow Bowl forensic audit report delayed, again (March 17, 2017)
Camden's Snow Bowl audit results delayed, no decision on DEP consent agreement, yet
Camden and the Snow Bowl redevelopment: One citizen's inquiry into the cash flow (Feb. 2, 2017)
Camden Snow Bowl Manager resigns; Camden commences new town manager search (Jan. 27, 2017)
Camden Town Manager resigns (Jan. 18, 2017)• Tacos, fat bikes and demo skis at the Camden Snow Bowl this weekend
• Camden orders Snow Bowl financial audit; to negotiate with Sidecountry, Cold Toes Tacos
• Following public outcry, Camden Select Board moved to help put two entrepreneurs back at Snow Bowl (Jan. 11, 2017)
• Camden, Rockland entrepreneurs told not to set up shop at Snow Bowl this weekend (Jan. 7, 2017)
• Camden Select Board pledges oversight of Snow Bowl spending, approves $920,000 budget (Aug. 4, 2016)
• Shaping the Camden Snow Bowl budget: Spend more to make more, or rein it in? (August 4 2016)
• Camden voters approve dipping into surplus to cover Snow Bowl's $297,303 deficit
• Camden Select Board forms new Ragged Mountain committee to advise the Snow Bowl (June 7, 2016)
• Camden Select Board chastises itself for Snow Bowl deficit, forms new committees to help
• Camden leaders make plan to reduce Snow Bowl's two-year deficit
• What to do about the Camden Snow Bowl’s $260,000 deficit
Sales, revenue up for season ski passes up at Camden Snow Bowl
• Camden readies Snow Bowl for new season; ticket, season pass price increases included (July 20, 2015)
Camden approves Ledgewood contract for phase 2 of mountain work (May 20, 2015)
• With record snowfall, Camden's Ragged Mountain Recreation Area begins making financial headway
• Camden Snow Bowl Redevelopment Committee, Ragged Mountain Foundation hold community meeting (March 2, 2015)
• Camden Snow Bowl project up to $8.4 million, fundraising resumes (Feb. 3, 2015)
• Making tracks in some dreamy snow at Camden Snow Bowl (Jan. 30)
• Snow Bowl to fire up chairlifts; refunds offered to passholders (Jan 21)
• Camden Planning Board to begin Snow Bowl lodge review (Jan. 9)
Camden Select Board brings in old friend to help with Snow Bowl progress (Jan. 7)
• Camden Snow Bowl to start making snow Jan. 5 (Jan. 2)
• Snow Bowl progress report to Camden Select Board continues to be positive (Dec. 3)
• One by one, 20 chairlift towers went up at the Camden Snow Bowl (Dec. 1)
• Helicopter to help raise, place 23 chairlift towers at Camden Snow Bowl (Dec. 1)
• Report: Ragged Mountain Redevelopment Project $500,000 over budget (Oct. 8)
• Camden Planning Board approves Snow Bowl lighting plan as proposed (Oct. 6)
• Camden Snow Bowl on target for Dec. 20 opening, weather willing (Sept. 19)
• Camden to contract with South Portland firm to manage Snow Bowl lodge, base area (July 24, 2014)
• Camden Snow Bowl project remains under DEP scrutiny, making progress, more work ahead (July 11)
• Vermont trail builder takes helm with Camden Snow Bowl project, new phase gets under way (July 10)
Camden Snow Bowl prepped for more rain, assembling working group to assist with next steps (July 2)
• Snow Bowl mountain mud runoff causes headache for neighbors, town (July 1)
• Camden Snow Bowl anticipates ending season in the black; work begins on Ragged Mountain (March 19)
• Homage to Camden’s Big T (March 15, 2014)
• By wide margin, Camden voters approve Snow Bowl improvement bond (Nov. 5, 2013)
• Camden voters consider $2 million Snow Bowl bond, three zoning amendments (Nov. 3, 2013)
• Camden committee selects new parks and recreation director (Sept. 6, 2013)
• Camden considers $2 million Snow Bowl bond, ordinance amendments Nov. 5 (Sept. 4, 2014)
• Camden ready to put $2 million bond before voters (Aug. 21, 2013)
• Camden pursues federal money to help with Snow Bowl upgrade (July 10, 2013)
• Camden learns about refurbished chairlifts, woven grips and haul ropes (April 10, 2013)
• Last run for Jeff (Jan. 21, 2013)
• Stellar start to season at Camden Snow Bowl (Jan. 9, 2013)
• Camden’s Ragged Mountain loses a good friend (Nov. 7, 2012)
• Ready for packed powder? Camden Snow Bowl to make it quicker, sooner with updated snow guns (Sept. 12, 2012)
Reach Editorial Director Lynda Clancy at lyndaclancy@penbaypilot.com; 207-706-6657
Event Date
Address
United States