Rep. Pluecker ‘thankful’ for infrastructure investment in Appleton, Hope, Union, Warren

Thu, 01/28/2021 - 1:00pm

    WARREN — House District 95 Representative Bill Pluecker, I-Warren, welcomes $7,341,000 worth of road and bridge construction coming to Appleton, Hope, Union and Warren as part of the Maine Department of Transportation 2021-2022-2023 Plan. 

    “One of the most important jobs our state has is the upkeep and maintenance of our roads and byways,” said Rep. Pluecker. “Without effective transportation, our economy, access to food, and access to healthcare all crumble. I am thankful that we are seeing the much needed investment in our infrastructure come to our district in these difficult times.” 

    Each January, MaineDOT produces a three-year comprehensive work plan that includes capital projects, maintenance and operations activities, planning initiatives, and administrative functions performed by MaineDOT and its transportation partners that receive federal funds directly (such as airports and transit agencies). The 2021 Edition (which covers calendar years 2021, 2022, 2023) includes 2,080 work items with a total value of $2.71 billion.

    2021

    Route 105 - Appleton, Camden, Hope: Replacing culverts in various locations on Route 105 in Appleton, Hope, and Camden. Beginning 0.80 of a mile south of the Searsmont Road and extending south 8.65 miles to the Hoffses Drive in Camden. $300,000

    Route 105 - Appleton, Hope: Ditching and replacing culverts in various locations on Route 105 in Appleton and Hope. Beginning with Route 131 and extending southwest 11.56 miles to Route 1. $59,000

    Barnestown Road - Camden, Hope: Ditching and replacing culverts in various locations on the Barnestown Road in Camden and Hope. Beginning at Route 235 and extending southwest 7.10 miles to Route 1. $33,000

    Route 235 - Hope, Lincolnville: Light Paving Beginning at Route 105 and extending northeast 3.01 miles to Route 173. $121,000

    Route 131 - Thomaston, Union, Warren: Light Paving Beginning 0.02 of a mile north of Route 1 and extending north 10.38 miles. $416,000

    Common Road - Union: Light Paving Beginning at Heald Highway and extending southeast 1.15 miles to South Union Road. $46,000

    Route 90 - Rockland, Rockport, Warren: Drainage Improvements Beginning 0.20 of a mile north of Mountain Road and extending north 7.19 miles. Includes 0.03 of a mile on Route 90 westbound. $168,000

    2022

    Barnestown Road - Camden, Hope: Light Paving Beginning at Hatchet Mountain Road and extending southeast 7.02 miles to Route 1. $368,000

    Route 131 - Appleton, Belmont, Searsmont, Union: Light Paving Beginning at Route 17 and extending north 15.44 miles. $809,000

    2022/2023

    Route 17 - Union: Culvert Replacement Located 0.06 of a mile east of Town House Road. $790,000

    Route 90 - Rockland, Rockport, Warren: Road Overlay Beginning 0.20 of a mile north of Mountain Road and extending north 7.19 miles. Includes 0.03 of a mile on Route 90 westbound. $2,930,000

    Route 1 - Thomaston, Warren: Bridge Rehabilitation James Andrew Griffith Bridge (#2786) over St. George River. Located on the Warren - Thomaston town line. $300,000

    Route 235 - Warren: Culvert Replacement Located 0.06 of a mile north of the Waldoboro town line. $420,000

    Route 90 - Warren: Bridge Rehabilitation St. George River Bridge (#5654) over St. George River. Located 0.04 of a mile southwest of Company Lane. $381,000

    Main Street - Warren: Drainage Improvements Beginning 0.09 of a mile east of Western Road and extending east 0.25 of a mile. $200,000