Thomaston Route 1 reconstruction project update
This is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Please be advised work areas may change as needed. Please use caution when navigating the work zones.
MONDAY, Aug. 1
• Install underdrain pipe from Green St to Georges St, Southbound lane
TUESDAY, Aug. 2
• Install underdrain pipe from Green St to Georges St, Southbound lane
WEDNESDAY, Aug. 3
• Install underdrain pipe from Green St to Wadsworth St, Southbound lane
THURSDAY, Aug. 4
• Install underdrain pipe from Green St to Wadsworth St, Southbound lane
FRIDAY, Aug. 5
• Install underdrain pipe from Green St to Wadsworth St, Southbound lane
MONDAY, Aug. 8
• Install underdrain pipe from Green St to Wadsworth St, Northbound lane
TUESDAY, Aug. 9
• Install underdrain pipe from Green St to Wadsworth St, Northbound lane
WEDNESDAY, Aug. 10
• Install underdrain pipe from Green St to Wadsworth St, Northbound lane
THURSDAY, Aug. 11
• Install underdrain pipe from Green St to Wadsworth St, Northbound lane
FRIDAY, Aug. 12
• Install underdrain pipe from Green St to Wadsworth St, Northbound lane
Supporting Main St., Thomaston:
In the weeks to come the project Facebook Page will be used on a regular basis to begin promoting Thomaston Businesses and events. To make sure you know what is going on, ‘Like’ the project on Facebook at: https://www.facebook.com/ThomastonProject
Reminder of ways to be up to date for alerts besides the email blast:
• MaineDOT Thomaston Route 1 Project Alerts: Sign up for email alerts at www.mainedot.gov
If you have any questions, contact Audrey Lovering at audreylovering@gmail.com or (207) 899-6925