Thomaston Route 1 construction update
Town of Thomaston Update #37 - August 25, 2017
WORK SCHEDULE: August 28th- September 8th
This is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Be advised work areas may change as needed. Please use caution when navigating the work zones.
MONDAY 28th
• Excavate & Gravel Sidewalks - Wadsworth St to Green St TUESDAY 29th
• Excavate & Gravel Sidewalks - Wadsworth St to Green St WEDNESDAY 30th
• Excavate & Gravel Sidewalks - Wadsworth St to Green St THURSDAY 31st
• Excavate & Gravel Sidewalks - Wadsworth St to Green St FRIDAY 1st
• Clean site, off road by noon MONDAY 4th
• LABOR DAY NO WORK
TUESDAY 5th
- Raise Catch Basins – Wadsworth St to Green St
- Finegrade Shoulders – James Griffith Bridge to Oyster River Rd
- WEDNESDAY 6th
- Pave 12.5mm 2nd Lift – James Griffith Bridge to Oyster River Rd
- Finegrade Sideroads – Main St Mall & School St
- Raise Catch Basins – School St to Ship St
- THURSDAY 7th
- Excavate & Gravel Sidewalks – Wadsworth St to Shibles Ln
- Raise Catch Basins – School St to Ship St
- Pave 12.5mm 1st Lift – Main St Mall & School St
• Finegrade Sideroads – Water Tower Rd & Toll Bridge Rd
FRIDAY 8th
- Excavate & Gravel Sidewalks – Wadsworth St to Shibles Ln
- Raise Catch Basins – School St to Ship St
- Prepare Curb Pavement – Beechwood St to Fish St
- Pave 12.5mm 1st Lift – Water Tower Rd & Toll Bridge Rd After Labor Day one-way traffic will resume on the MaineDOT Rte 1 Project. This is in accordance with the contract between MaineDOT and Lane Construction. Just like last fall, Lane Construction will work hard to keep traffic flowing and use one-way traffic on an as needed base particularly when it is unsafe to use two-way traffic. Town officials, MaineDOT, and Lane Construction realize the impact one-way traffic has on the businesses, community, and commuters and are working hard to limit its use. However, it is unrealistic to predict daily when and for how long one-way traffic will be used. Questions or Concerns
- If you have any questions, problems, or concerns please contact Audrey Lovering at audreylovering@gmail.com or (207) 899-6925.
- THOMASTON BUSINESSES - Thank you for continuing to shop and support Thomaston businesses.
- ONE –WAY TRAFFIC RETURNING