    Town of Thomaston Changes to Update #11 August 17, 2016: The following changes have been made to the MaineDOT Route 1 Thomaston Project's schedule.

    There will be a change in Traffic and Parking Pattern next week. Roadside parking will now be impacted next Monday and Tuesday near Knox Street. The change in parking is due to the need to shift traffic in order to maintain 2 way traffic while completing the storm drain work on Knox Street. However, there is plenty of parking behind the Block Buildings to allow people to continue to access the businesses.

    August 18 – August 26

    THURSDAY 18

    • Install underdrain pipe from Green St to Wadsworth St, Southbound & Northbound lanes FRIDAY 19th

    • Install underdrain pipe from Green St to Wadsworth St, Southbound & Northbound lanes

    MONDAY 22

    Install underdrain pipe from Green St to Wadsworth St, Northbound lane
    Install drainage at Knox St and crossing Route

    TUESDAY 23
    Install underdrain pipe from Green St to Wadsworth St, Northbound lane
    Install drainage at Knox St and crossing Route 1

    WEDNESDAY 24
    Install underdrain pipe from Green St to Wadsworth St, Northbound lane
    Install underdrain pipe from Water Tower Rd to Wadsworth St, Northbound lane

    THURSDAY 25
    Install underdrain pipe from Green St to Wadsworth St, Northbound lane
    Install underdrain pipe from Ship St to Wadsworth St, Northbound lane

    FRIDAY 26
    Install underdrain pipe from Green St to Wadsworth St, Northbound lane
    Install underdrain pipe from Ship St to Wadsworth St, Northbound lane