Thomaston Route 1 construction project update
This is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Be advised work areas may change as needed. Please use caution when navigating the work zones.
April 28 - May 5
FRIDAY, April 28
Common Excavation & Gravel – Toll Bridge Rd to Oyster River Rd
Repair Concrete James Griffith Bridge – Northbound Lane
MONDAY, May 1
Common Excavation & Gravel – Oyster River Rd
Raise Sewer Frame & Covers – Beechwood St to Erin St
Finegrade Driveways – Erin St to Fish St
Electrical Work – Burton Block, Beechwood Ave South Corner, Watts Hall North Corner
Repair Concrete James Griffith Bridge – Northbound Lane
Common Excavation & Gravel – Oyster River Rd
Raise Sewer Frame & Covers – Beechwood St to Erin St
Finegrade Driveways – Erin St to Fish St
Electrical Work – Burton Block, Beechwood Ave South Corner, Watts Hall North Corner
Repair Concrete James Griffith Bridge – Northbound Lane
Common Excavation & Gravel – Shibles Ln to Toll Bridge Rd
Finegrade Driveways – Gilchrest St to Erin St
Pave Driveways – Erin St to Roxbury St
Electrical Work – Burton Block, Beechwood Ave South Corner, Watts Hall North Corner
Install Membrane James Griffith Bridge – Northbound Lane
Common Excavation & Gravel – Shibles Ln to Toll Bridge Rd
Finegrade Driveways – Gilchrest St to Erin St
Pave Driveways – Dwight St to Fish St
Place Base Pavement James Griffith Bridge – Northbound Lane
Common Excavation & Gravel – Shibles Ln to Toll Bridge Rd Finegrade Driveways – Gilchrest St to Erin St
Pave Driveways – Dwight St to Fish St
Place Protective Coating James Griffith Bridge – Northbound Lane
- If you have any questions, problems, or concerns, contact Audrey Lovering at audreylovering@gmail.com or (207) 899-6925.